PROJECT COSTS / Coming soon

Job Cost & Profit Tracker

A two-tab Excel workbook with 200 cost entries, category budgets and a cost-to-finish forecast. Includes a PDF guide and worked example.

Checkout coming soon

Planned price: $29 USD / one-time download
2-tab Excel workbook + 3-page PDF guide

Job Cost & Profit Tracker product cover

What is included

  • 200 cost entries
  • Budget vs recorded costs
  • Forecast profit and margin

2-tab Excel workbook + 3-page PDF guide. START-HERE instructions and an internal-use license are included in the ZIP.

How you will use it

1. Start with the contract

Save a copy per job. On Job cost, enter a project name, the original contract and approved changes only. Enter monetary values in USD.

2. Set the budget

Enter budgets for Materials, Labor, Equipment, Subcontractors, Travel and Other. A blank budget is unavailable; zero is an intentional zero budget.

3. Record the actual charges

On Cost log, enter each cost once with a category, description, quantity, unit, unit rate and record reference. Use quantity 1 for a lump sum. Use negative quantity for a credit.

4. Enter the cost to finish

Forecast profit stays blank until you enter the remaining cost forecast. Enter zero only when no more cost is expected. Other overhead must exclude costs already in the log or forecast.

5. Review exceptions

Check uncategorized costs and lines needing input. The overall recorded total includes calculable uncategorized charges; category totals use the listed categories.

A fictional worked example

Input / resultFictional example
Original contract + approved changes$20,000 + $1,000 = $21,000
Materials10 units x $250 = $2,500
Labor100 hours x $50 = $5,000
Equipment5 days x $100 = $500
Recorded job costs$8,000
Other overhead + cost to finish$500 + $3,000
Forecast total cost$11,500
Forecast job profit / margin$9,500 / 45.24%

Forecast cost = recorded costs + other overhead + cost to finish. Forecast job profit = revised contract minus forecast cost. Forecast margin = forecast job profit divided by revised contract. A zero contract has no meaningful margin, shown as n.a. Category variance is recorded cost minus entered budget; a positive variance is over budget. This is a cost forecast, not a revenue-recognition, tax, payroll or cash-collection system.

Inside the workbook

Actual template preview. Amber cells are editable; calculated fields stay separate.

Actual Job Cost & Profit Tracker spreadsheet preview

Software and use

Delivered as an editable .xlsx workbook and PDF guide. Compatible spreadsheet software and a PDF reader are required. No macros. Formulas and status changes were checked in the authoring engine; desktop Excel and Google Sheets import have not been independently tested. Desktop use is recommended for the wide tables.

One purchase covers internal use by one business and its employees/project teams. Completed project records may be shared with customers; resale or redistribution of blank products is not included.

This product is coming soon and cannot be purchased yet. Browse the available calculator, books and tools in the shop.

Browse the shop →
Product questions? Contact Steel & Grit.